Sprints
 

Sprint 1

Sprint goal:

Make sure that we have a good foundation for future development

 

Sprint backlog: 

  • Design database (5h)

  • Git (20h)

  • Design front end (25h)

  • Create database (20h)

  • Server (80h)

  • Learn the underlying technologies (70h)

Total: 220h

Sprint 2

Sprint goal:

Create a functional user interface for the application Connect the frontent to a backend, filled with data.  


 

Sprint backlog: 

  • Main page (30h)

  • Gather data about Stockholm (80h)

  • Liked sights page(40h)

  • Settings page (20h)

  • Chose tags page (20h)

  • More info page (13h)

Total: 203h

Sprint 3

Sprint goal:

Alpha version of CultureGO

 

Sprint backlog: 

Authentication (40h)

Recommendation algorithm (80h)

Swipe function(13h)

Functional database (60h)

 

Total:193h

Sprint 4

Sprint goal:

CultureGO v1.0

 

Sprint backlog: 

  • Hosting (13h)

  • Expo site (10h)

  • Managing dislikes (20h)

  • Fill database (100h)

  • Tag values (10h)

  • Fine tuning (40h)

Totalt: 193h